Dhaka Mass Transit Company Ltd.

Construction Updates

The construction of respective contract packages will begin as they are awarded to the deserving bidders.
Please click on the contract package to get the relevant construction update.  

Contract packages and construction updates

Contract

Packages

Package Description

Commencement

Percentage complete

CP-01 Depot Land Development

8th September, 2016

68%

CP-02

Civil & Building works of the Depot

14th September, 2017   

CP-03

&

CP-04

CP-03 is for the construction of Viaducts and Elevated Stations from Uttara North to Pallabi.

CP-04 is for the construction of Viaducts and Elevated Stations from Pallabi to Agargaon.

 1st August, 2017  

CP-05

&

CP-06

CP-05 is for the Construction of Viaducts and Elevated Stations from Agargaon to Karwan Bazar.

CP-06 is for the Construction of Viaducts and Elevated Stations from Karwan Bazar to Motijheel.

   
CP-07

CP-07 is for the Electro-Mechanical (E&M) systems.

The contract will be on design-build basis.

   
CP-08

CP-08 is for the supply of Rolling Stock & Depot Equipment.

The contract will be on design-build basis.

14th September, 2017   
 

 This page was updated as of September, 2017

 