Dhaka Mass Transit Company Ltd.

CP-07 (Electro-Mechanical Systems)

CP-07 is for the Electro-Mechanical (E&M) systems of MRT Line-6. The contract shall be on design-build basis. 
  • The invitation for PQ application of CP-07 was published on 18th March, 2015.
  • A Corrigendum Notice with revised dates was published on 15th May, 2015.  
  • A total of 31 (Thirty One) PQ applications were sold.
  • The date of PQ application submission was 13th July 2015.
  • 4 (Four) PQ applications were submitted. 
  • PQ Evaluation Report was sent to JICA for concurrence on 18th November 2015.
  • JICA conferred its concurrence regarding Tender Evaluation on 10th January, 2016.
  • The concerned Evaluation Report was approved by the DMTC Board on 2nd March, 2016.
  • The concurrence of JICA regarding Bid Document was received on 2nd May, 2016.
  • The Bid call invitation to the prequalified bidders was announced on May 26, 2016.
  • The last date of Bid submission was January 30th, 2017. The Bid was opened on the same date and only 1 (One) Bid was received.
  • The evaluation activities are under process.
 

This page was last updated as of September, 2017

Top