Package CP-05 is for the Construction of Viaducts and Elevated Stations from Agargaon to Karwan Bazar.
Package CP-06 is for the Construction of Viaducts and Elevated Stations from Karwan Bazar to Motijheel.
 
  • JICA's concurrence on PQ Document of CP-5 & CP-6 was requested on 22nd May, 2016.
  • JICA's concurrence was received on 12 June, 2016 and it was approved by Board of Directors on 25th September, 2016.
  • The PQ application was invited on November 1st, 2016.
  • The last date of PQ submission was 17th January, 2017.
  • 21 (Twenty One) PQ applications (schedules) were sold.
  • The tender was opened on January 17th, 2017.
  • 6 (Six) tenders were received.
  • The process of tender evaluation was completed on March 30th, 2017.
  • The PQ Evaluation Report was approved by the DMTCL Board on May 17th, 2017.
  • The Bid was invited to the Pre-Qualified Bidders on 13 July, 2017.
  • The date of submission of Bids is 15 November, 2017.
  • The CP-05 contract for BDT 1854,69,70,403/- (including Vat-Taxes) for the Construction of 3.20 Kilometer Viaduct and 3 Stations between DMTCL and Tekken-AML-Abenikko JV [Tekken Corporation (Japan)-Abdul Monem Ltd. (Bangladesh)-AB Nikko Kogyu Co., Ltd. (Japan) JV] was signed on 30 April, 2018.
  • The CP-06 contract for BDT 2332,03,11,015/- (including Vat-Taxes) for the Construction of 4.92 Kilometer Viaduct and 4 Stations between DMTCL and SMCC-ITD JV [Sumitomo Mitsui Construction Co., Ltd (Japan) and Italian-Thai Development Public Company Ltd. (Thailand) JV] was signed on 30 April, 2018.